Estimating cost
The most reliable estimate adds up the cost of each work package (bottom-up). When there is no detail yet, compare with a similar past project (analogous) or multiply a known rate by a quantity (parametric). Add the pieces, add a reserve for known risks, and the approved total becomes the budget baseline you track against.